Contract BondsSubdivisionLicense & PermitAll BondsBond CalculatorGuidesFormsAboutGet a Bond →
All 50 statesA-rated surety carriersSame-day bid bondsEst. 2012
Underwriting

The WIP schedule, column by column: what each number tells your surety

A WIP schedule tells your surety whether your jobs will finish where you said. Here is what each column means and what underwriters compute from it.

20266 min read

A work-in-progress schedule is a job-by-job report showing, for every contract you have open, what you agreed to build, what you thought it would cost, what it has cost so far, how much you have billed, and what is left to finish. A surety underwriter reads it to answer one question: are your jobs going to finish where you said they would? Your capacity, your rate, and your single-job limit all follow from the answer.

The columns, and what each one is for

  • Contract amount — the original contract plus approved change orders. Unapproved change orders do not belong here, and carrying them is one of the fastest ways to lose credibility with an underwriter.
  • Estimated total cost — your current best estimate of what the job will cost to complete. Not the original bid.
  • Estimated gross profit — contract amount less estimated total cost. This is the number tracked period over period.
  • Cost incurred to date — actual cost booked against the job.
  • Percent complete — cost incurred to date divided by estimated total cost.
  • Earned revenue — percent complete multiplied by the contract amount.
  • Billed to date — what you have actually invoiced.
  • Over- or underbillings — the difference between billed to date and earned revenue.
  • Estimated cost to complete — estimated total cost less cost incurred to date.
  • Backlog — contract amount less earned revenue.

Percent complete, and why cost-to-cost is the method that counts

Effectively every surety works from the cost-to-cost method: percent complete equals cost incurred to date divided by estimated total cost. It is not a judgment about how far along the job feels or how many units are in place. It is arithmetic on two numbers you control.

That matters because it makes the schedule self-policing. Understate estimated total cost and percent complete rises, earned revenue rises with it, and the job looks more profitable than it is — right up until the remaining cost catches you and the margin collapses in a single period. Underwriters have seen that pattern many times, which is why they read the trend across periods rather than the snapshot in front of them.

Overbillings and underbillings

Earned revenue is what you have arguably earned. Billed to date is what you have asked for. The gap between the two is one of the most informative numbers on the schedule.

Overbillings — billings in excess of costs and estimated earnings — mean you have invoiced ahead of the work. That supports cash flow, and modest overbilling is normal and healthy. Heavy overbilling across the whole schedule is a different signal: the business is being funded by owners paying for work not yet performed, and if that work stops, the cash has to be returned in the form of performance.

Underbillings — costs and estimated earnings in excess of billings — mean you have performed work you have not been paid for. Sometimes that is simple timing. Often it is unapproved change orders, disputed quantities, or costs running past what the billing schedule allows. Persistent underbillings on one job are a common early signal of a job in trouble.

Profit fade is the first thing checked

Profit fade is the decline in a job's estimated gross profit from one reporting period to the next. If a job was carried at a 12% margin in the first quarter, 9% in the second, and 6% in the third, it is the fade the underwriter is reacting to — not the 6%.

Fade matters more than the absolute margin because it says something about estimating discipline, and estimating discipline is closer to what a surety is actually underwriting. One faded job with a clear explanation — a differing site condition, a subcontractor default — is a conversation. A pattern of fade across several jobs is a capacity problem.

The schedule has to tie to your financial statements

This is the check that catches the most contractors. Underbillings should appear on the balance sheet as a current asset. Overbillings should appear as a current liability. Revenue and cost of revenue on the income statement should agree with what the schedule produces.

When the WIP does not reconcile to the financials, the underwriter cannot rely on either document. That is a worse position than a schedule showing bad news, because bad news can be explained and an unreliable schedule cannot.

Concentration and backlog

The last read is structural. How large is your biggest job relative to the rest of the schedule, and relative to your working capital? A schedule where one contract dwarfs everything else raises the single-job limit question directly. Backlog — contract amount less earned revenue, summed across every job — tells the surety how much work you still have to perform on the same working capital and the same crews.

What to do with it

Understanding the columns is the first half. The second half is presenting the schedule so it works in your favour: keeping it current, reconciling it before you send it, and having an explanation ready for any job carrying an unusual position. That is covered in our guide, How Underwriters Read Your WIP Schedule, and a consistent WIP template is on the Resources page.

Frequently asked

What is a WIP schedule?

A work-in-progress schedule is a job-by-job report showing, for every contract in progress, the contract amount, estimated total cost, cost incurred to date, percent complete, earned revenue, amount billed to date, and estimated cost to complete. Sureties require one alongside your financial statements.

How is percent complete calculated on a WIP schedule?

Using the cost-to-cost method: cost incurred to date divided by estimated total cost. Multiplying that percentage by the contract amount gives earned revenue for the period.

Are underbillings bad?

Not automatically. Timing differences between performing work and invoicing it are normal. Persistent underbillings on a single job usually point to unapproved change orders or costs running past the billing schedule, and that will draw questions.

What is profit fade?

Profit fade is the decline in a job's estimated gross profit from one reporting period to the next. Underwriters watch the trend rather than the current margin, because consistent fade indicates the original estimate was optimistic.

How often does a surety want an updated WIP schedule?

Most sureties want one at least quarterly, and monthly for larger bonding programs or when a job is in trouble. Your agent can tell you what your specific carrier expects.

Have a bond coming up?

Send us the form and the amount — we'll confirm requirements and get it issued, often the same day.

Start Your Bond Request

One form, every bond type — or chat with us and we'll confirm requirements right away.

All bond types — contract, subdivision & commercial

Request a Bond

One form for every bond request — we'll confirm requirements and route it right away.

or chat with us now
Chat with usOur team typically responds within minutes

✓  We'll review your submission, confirm any missing details, and follow up with a quote or next steps — typically within 1 business hour during business hours.

Available Mon–Fri — or leave a message and we'll follow up same day.

Call Us — 610-489-6168
Get a BondForms